The Central Florida Expressway Authority will be putting shovels in the dirt this year for several projects as it continues work on others that will help connect residents and visitors in the region and reduce congestion.
Here’s what’s on the authority’s radar this year that may affect your commute:
- State Road 408 resurfacing from State Road 50 to Ortman (Mercy) Drive, then from Ortman (Mercy) Drive to Westmoreland Drive. Work begins Jan. 14 and is estimated to cost more than $8.6 million.
- State Road 417 widening from Econlockhatchee River to the Orange/Seminole County line. Work is expected to begin this spring and is projected to cost $28.7 million.
- State Road 429/County Road 535 northbound entrance ramp improvements. Work is expected to start in the fall and is projected to cost $4 million.
Be sure to read the full original article that can be found by clicking here.